Central Richmond Home Remodel: A Project Journal

By Solid Bay Construction SF | Updated 2026

We're currently mid-project on a full remodel in San Francisco's Central Richmond neighborhood: a 3rd story addition, a complete foundation retrofit, and a full interior gut and rebuild. This page follows the actual construction — real photos, updated as the work progresses, not a rendering or a stock case study.

The Scope of Work

Full Interior Demo

Before any structural work begins, the interior comes down to studs. This lets us verify the actual framing condition — not just what's on the original permit drawings — and catch anything that needs to be addressed before the addition and foundation work move forward.

Central Richmond home interior gutted to framing, ready for structural work
Full interior gut — framing exposed and ready for structural work.
Demolition debris and exposed framing during full home gut in San Francisco
Demo complete — stripped to studs throughout.

Why This Home Needed New Foundation Work

You can't add a 3rd story to a house without confirming the foundation can carry the extra load — and in the Central Richmond, that check almost always turns up work that needs to happen. Much of the Outer and Central Richmond was built on reclaimed dune sand in the early 20th century, and many of these homes still sit on the original, undersized 1920s–1940s foundations. Adding weight above without reinforcing what's below is how you end up with cracked stucco, uneven floors, and settlement issues years down the line.

For this project, that meant a full foundation retrofit: excavating along the perimeter, tying in new rebar cages, and pouring reinforced concrete stem walls and pier footings sized for the new 3rd story load — not just patching what was already there.

Foundation Excavation, Rebar & Pour

Foundation excavation underway beneath San Francisco home
Foundation excavation underway.
New foundation stem wall formed with plywood along excavated trench
New foundation stem wall formed.
Rebar cage tied and set in footing trench along house foundation
Rebar cage tied and set in the footing trench.
Freshly poured concrete foundation wall, still wet
Foundation wall poured.
Cured and finished concrete foundation wall
Foundation wall finished and cured.
New concrete pier footing with anchor bolts set for structural framing
New concrete pier footing with anchor bolts set.

What's Next

With the foundation work complete, the next phase is framing the 3rd story addition and roughing in new electrical and plumbing throughout the house. We'll keep updating this page and the project gallery on our homepage as it moves forward.